A plot, a consent, a building, a tenancy
This company buys and sells its own interests in land and buildings, develops building projects on them, and lets and operates what it keeps. It works as principal: there is no client on the other side of this work.
Read the margin first: a stage that cannot lawfully begin until a piece of paper exists has its date set by that paper, not by the diary.
The thing that changes hands00 · before the sequence
A development starts as ground with a line around it. What is bought is paper: a registered title and a plan with an edge marked on it.
Drawn for this page; not a site of this company's.
Plot acquisition01 · title only
The register and the title plan say what is registered against the land, and the covenants, easements and rights of way are read in full, because a covenant against building or a drain crossing the rear decides the scheme before an architect is instructed.
Register Official copies come from the registry, never from the seller's file.
Searches are ordered at the same time: local land charges and the local authority enquiries, drainage and water, environmental, and a mining search where the ground history calls for one.
Searches A reply that lands after exchange has landed too late.
Selling on is the same code read backwards: a plot can be bought and resold with no building work at all. Either way the land transaction return is filed within the statutory period and the transfer registered afterwards.
After completion Two filings, two clocks, neither optional.
What the ground will holdfour links, worked on screen
Consent02 · application
Planning permission and building control approval are two separate consents, and holding one is no evidence of the other. The planning application is made in full, or in outline with matters reserved, and is publicised, consulted on and determined under delegated powers or at committee.
A permission arrives with conditions. Pre-commencement conditions are discharged in writing before any work starts; pre-occupation conditions fall due before the building is used; the rest run with the permission for its life. Planning obligations, where required, are entered into by agreement and bind the land. Liability for the infrastructure levy is assumed in writing before commencement.
The rule this office keeps its diary to
Work begun before a pre-commencement condition is discharged can be unauthorised even where the permission itself is sound.
So the diary runs from the discharge decision and not from the grant. The condition is discharged on its own application, in its own period.
Construction03 · conditions
The sequence on site is fixed by what has to be covered up. Drainage is laid and tested before it is buried, and where a public sewer runs near the works a build-over agreement is settled with the water authority first. Substructure rises to damp-proof course, superstructure after it, and the roof makes the building watertight so that first fix, plaster, second fix and external works run dry.
Building control inspects at set points rather than continuously, each point the last moment at which that work can still be seen. Where the works affect a shared wall or a neighbour's foundations, notices go to the adjoining owners under the party wall legislation, each class with its own period before work may begin.
When the clock lets work beginruled, dates in full
Practical completionbetween build and tenancy
Practical completion is recorded, the snagging list worked through, and a defects period runs from that date with any retention released against it. The as-built drawings, manuals and certificates go into one file.
What a consent actually carries
A permission is rarely a single permission. It arrives with conditions attached, and the conditions are not equal: some must be discharged before anything happens on site, and the rest run alongside the work or bind the finished building. Reading them in that order is the whole of programme control at this stage.
- Pre-commencement
- Nothing lawful can start until these are discharged in writing. Typically ground investigation and remediation strategy, a construction method statement, tree protection, and surface-water drainage. Each is a separate application with its own determination period.
- Pre-occupation
- Work may proceed; the building may not be used. Parking and cycle provision, landscaping, boundary treatment, and any off-site highway works.
- Compliance
- Binding for the life of the building and discharged by doing the thing: materials as approved, hours of operation, no permitted-development rights where they have been removed.
The mistake that costs a programme is treating all three as one list and submitting them together. A pre-commencement condition submitted late stops the job; a compliance condition submitted early is simply filed.
Pre-commencement planner
How many pre-commencement conditions, and when they went in. The planner gives the earliest lawful start, on the statutory eight-week determination period for a discharge application, with submissions assumed in parallel rather than one after another.
What a unit has to satisfy before a tenancy starts
A building that is finished is not the same as a unit that can be let. The gap between the two is a short list of documents and a longer list of conditions, and every one of them has to exist on the day the tenancy begins rather than shortly afterwards.
- Electrical installation condition report. In force at the start of the tenancy, on a five-year cycle, with any C1 or C2 observation remedied and the remedial confirmation held with the report.
- Gas safety record. Where there is a gas appliance: an annual check, the record given before occupation, and a copy held.
- Energy performance certificate. At or above the minimum band for a lettable dwelling, with the certificate itself — not the recommendation report — given to the incoming tenant.
- Smoke and carbon-monoxide alarms. One smoke alarm per storey, a CO alarm in any room with a fixed combustion appliance other than a gas cooker, and both tested on the first day of the term.
- Deposit protection. Taken into an approved scheme within the statutory period, with prescribed information served; without it a notice later cannot be relied on.
- Right to rent. Checked on the original documents before the term begins, with the check dated and retained.
This company is the landlord of what it keeps, so the list is not advice to somebody else: it is the sequence the office runs in the fortnight before a unit is handed over, and a unit that fails any line of it does not get let until the line is closed.
First letting04 · completion
Four papers stand between a finished building and an occupied one.
- a Energy performance Lodged before the interest is marketed, not before it is occupied.
- b Deposit On a residential letting, protected in an approved scheme within the statutory period, with the prescribed information served.
- c Alarms One on each storey, and a carbon monoxide alarm wherever a fixed combustion appliance sits.
- d Commercial terms Schedule of condition taken before occupation; whether security of tenure is excluded settled before the lease completes.