Skip to the sequence
A new-build plot at golden hour: fresh brickwork rising to first-floor level, scaffold standards catching the light, levelled ground running away under a wide sky.
Brickwork to first floor on a single plot. Four stages separate this from a tenancy.

A plot, a consent, a building, a tenancy

This company buys and sells its own interests in land and buildings, develops building projects on them, and lets and operates what it keeps. It works as principal: there is no client on the other side of this work.

Read the margin first: a stage that cannot lawfully begin until a piece of paper exists has its date set by that paper, not by the diary.

FRONTAGE DEPTH ADJOINING OWNER RIGHT OF WAY CARRIAGEWAY EXISTING BUILDING N
The outline under the hoarding is what is actually bought: a boundary, the things that cross it, a frontage. The drawing is generic.

The thing that changes hands00 · before the sequence

An isometric render of a rectangular platform of bare earth cut out of scrubby ground. Timber stakes stand at intervals along all four edges with a line strung between them, a kerbed footway and a strip of carriageway run along the lower side, and the cut face of the ground is exposed at the far corner.

A development starts as ground with a line around it. What is bought is paper: a registered title and a plan with an edge marked on it.

Drawn for this page; not a site of this company's.

Plot acquisition01 · title only

The register and the title plan say what is registered against the land, and the covenants, easements and rights of way are read in full, because a covenant against building or a drain crossing the rear decides the scheme before an architect is instructed.

Register Official copies come from the registry, never from the seller's file.

Searches are ordered at the same time: local land charges and the local authority enquiries, drainage and water, environmental, and a mining search where the ground history calls for one.

Searches A reply that lands after exchange has landed too late.

Selling on is the same code read backwards: a plot can be bought and resold with no building work at all. Either way the land transaction return is filed within the statutory period and the transfer registered afterwards.

After completion Two filings, two clocks, neither optional.

What the ground will holdfour links, worked on screen

How much a plot will hold, link by link

Gross means gross — circulation, walls and plant are inside the figure — so the count is a ceiling and not an expectation. What a plot will take is settled by the authority, not by this arithmetic.

PLAN SECTION 45% cover 3 storeys · 1,620 m²

The rule this office keeps its diary to

Work begun before a pre-commencement condition is discharged can be unauthorised even where the permission itself is sound.

So the diary runs from the discharge decision and not from the grant. The condition is discharged on its own application, in its own period.

Construction03 · conditions

The sequence on site is fixed by what has to be covered up. Drainage is laid and tested before it is buried, and where a public sewer runs near the works a build-over agreement is settled with the water authority first. Substructure rises to damp-proof course, superstructure after it, and the roof makes the building watertight so that first fix, plaster, second fix and external works run dry.

Building control inspects at set points rather than continuously, each point the last moment at which that work can still be seen. Where the works affect a shared wall or a neighbour's foundations, notices go to the adjoining owners under the party wall legislation, each class with its own period before work may begin.

ROOF FLOOR DPC FOOTING DRAIN
Read from the bottom: nothing above a line is built until the line below it has been seen.

When the clock lets work beginruled, dates in full

Validation to the earliest start on site

The date the authority puts on its decision is the date that counts: a period entered here is the one this office expects, not the one it has been given.

Entered above the heavy rule, worked below it
Validated on the day the clock starts
Determination weeks
Discharge weeks
Determination 11 January 2027 + 8 weeks (56 days) 8 March 2027
Earliest start 8 March 2027 + 6 weeks (42 days) 19 April 2027
Total 8 + 6 weeks = 98 days 14 weeks

The determination date falls on a Monday and the earliest start on site on a Monday.

Practical completionbetween build and tenancy

An isometric render of a finished two-storey block with a flat roof, seen from above at an angle. A glazed ground floor, a run of vertical fins on the end bay, a canopy over the entrance, and paved aprons with planted strips and small trees along two sides.
Drawn for this page; not a building of this company's.

Practical completion is recorded, the snagging list worked through, and a defects period runs from that date with any retention released against it. The as-built drawings, manuals and certificates go into one file.

What a consent actually carries

A permission is rarely a single permission. It arrives with conditions attached, and the conditions are not equal: some must be discharged before anything happens on site, and the rest run alongside the work or bind the finished building. Reading them in that order is the whole of programme control at this stage.

Pre-commencement
Nothing lawful can start until these are discharged in writing. Typically ground investigation and remediation strategy, a construction method statement, tree protection, and surface-water drainage. Each is a separate application with its own determination period.
Pre-occupation
Work may proceed; the building may not be used. Parking and cycle provision, landscaping, boundary treatment, and any off-site highway works.
Compliance
Binding for the life of the building and discharged by doing the thing: materials as approved, hours of operation, no permitted-development rights where they have been removed.

The mistake that costs a programme is treating all three as one list and submitting them together. A pre-commencement condition submitted late stops the job; a compliance condition submitted early is simply filed.

Pre-commencement planner

How many pre-commencement conditions, and when they went in. The planner gives the earliest lawful start, on the statutory eight-week determination period for a discharge application, with submissions assumed in parallel rather than one after another.

What a unit has to satisfy before a tenancy starts

A building that is finished is not the same as a unit that can be let. The gap between the two is a short list of documents and a longer list of conditions, and every one of them has to exist on the day the tenancy begins rather than shortly afterwards.

  • Electrical installation condition report. In force at the start of the tenancy, on a five-year cycle, with any C1 or C2 observation remedied and the remedial confirmation held with the report.
  • Gas safety record. Where there is a gas appliance: an annual check, the record given before occupation, and a copy held.
  • Energy performance certificate. At or above the minimum band for a lettable dwelling, with the certificate itself — not the recommendation report — given to the incoming tenant.
  • Smoke and carbon-monoxide alarms. One smoke alarm per storey, a CO alarm in any room with a fixed combustion appliance other than a gas cooker, and both tested on the first day of the term.
  • Deposit protection. Taken into an approved scheme within the statutory period, with prescribed information served; without it a notice later cannot be relied on.
  • Right to rent. Checked on the original documents before the term begins, with the check dated and retained.

This company is the landlord of what it keeps, so the list is not advice to somebody else: it is the sequence the office runs in the fortnight before a unit is handed over, and a unit that fails any line of it does not get let until the line is closed.

First letting04 · completion

Four papers stand between a finished building and an occupied one.

  • a Energy performance Lodged before the interest is marketed, not before it is occupied.
  • b Deposit On a residential letting, protected in an approved scheme within the statutory period, with the prescribed information served.
  • c Alarms One on each storey, and a carbon monoxide alarm wherever a fixed combustion appliance sits.
  • d Commercial terms Schedule of condition taken before occupation; whether security of tenure is excluded settled before the lease completes.